What is the probability that the project can be completed in 23 days or less?Suppose it is now the end of the seventh day and
What is the probability that the project can be completed in 23 days or less?Suppose it is now the end of the seventh day and the activities A and B have been completed, while activity D is 50 percent completed. Time estimates for the completion of activity D are ?5, 6, and 7. Activities C and H are ready to begin. What is the probability of finishing the project by day 23? ?