Question
1 Approved Answer
What is the projects discounted payback? r = 10.00% Year Cash Flows 0 $800 1 $500 2 $500 3 $500 A. 2.09 years b. 1.44
What is the projects discounted payback?
r = 10.00%
Year Cash Flows 0 $800 1 $500 2 $500 3 $500
A. 2.09 years
b. 1.44 years
c. 2.45 years
d. 1.84 years
e. 1.65 years
What is the projects discounted payback?
r = 10.00%
Year | Cash Flows |
0 | $800 |
1 | $500 |
2 | $500 |
3 | $500 |
A. 2.09 years
b. 1.44 years
c. 2.45 years
d. 1.84 years
e. 1.65 years
Step by Step Solution
There are 3 Steps involved in it
Step: 1