Question

1 Approved Answer

What is true of the CPI? (You may select more than one answer. Single click the box with the question mark to produce a check

What is true of the CPI? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)

check all that apply

How does earned value give a clearer picture of project schedule and cost status than a simple plan versus actual system? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)

check all that apply

  • The earned value system includes the time variable in measuring progress.unanswered
  • The earned value system includes the cost variable in measuring progress.unanswered
  • Earned value measures what work was accomplished for the time spent.unanswered
  • Earned value measures what work was accomplished for the money spent.unanswered

What is true of BAC and EAC? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)

check all that apply

  • BAC factors in new cost estimates that have been made by project participants.unanswered
  • BAC is the planned budget at completion.unanswered
  • EAC can be determined using more than one method.unanswered
  • EAC is always an estimate.unanswered
  • BAC is a performance ratio.

What is true of the project baseline? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)

check all that apply

  • Scope changes can come from project personnel.unanswered
  • The usefulness of the baseline can be eroded by constantly changing it.unanswered
  • Changes in baselines should be limited to minor scope changes.unanswered
  • Natural disasters can force a baseline change.unanswered
  • Changes should only occur after a work package is complete.unanswered
  • Customers should not request scope changes.

PLEASE HELP! THANK YOU SO MUCH FOR YOUR TIME!

  • It is a cost performance index.unanswered
  • It is a time performance index.unanswered
  • An index of .80 suggests that the project may be under budget.unanswered
  • An index of .80 indicates that 80 cents of work has been completed for each actual dollar spent.unanswered
  • An index of 1.25 indicates that 25% more of the work has been completed than was planned by this time.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Forecasting And Predictive Analytics With Forecast X

Authors: Barry Keating, J. Holton Wilson, John Solutions Inc.

7th International Edition

1260085236, 9781260085235

More Books

Students also viewed these Finance questions

Question

Did you trace the accomplishments, issues, and milestones?

Answered: 1 week ago