Question
What should Tom Kemper do? Explain. Tom Kemper is the controller of the Wichita manufacturing facility of Prudhom Enterprises, Inc. The annual cost control report
What should Tom Kemper do? Explain.
Tom Kemper is the controller of the Wichita manufacturing facility of Prudhom Enterprises, Inc. The annual cost control report is one of the many reports that must be filed with corporate headquarters and is due at corporate headquarters shortly after the beginning of the New Year. Kemper does not like putting work off to the last minute, so just before Christmas he prepared a preliminary draft of the cost control report. Some adjustments would later be required for transactions that occur between Christmas and New Years Day. A copy of the preliminary draft report, which Kemper completed on December 21, follows:
Melissa Ilianovitch, the general manager at the Wichita facility, asked to see a copy of the preliminary draft report. Kemper carried a copy of the report to her office where the following discussion took place:
Ilianovitch: Ouch! Almost all of the variances on the report are unfavorable. The only favorable variances are for supervisory salaries and industrial engineering. How did we have an unfavorable variance for depreciation?
Kemper: Do you remember that milling machine that broke down because the wrong lubricant was used by the machine operator?
Ilianovitch: Yes.
Kemper: We couldnt fix it. We had to scrap the machine and buy a new one.
Ilianovitch: This report doesnt look good. I was raked over the coals last year when we had just a few unfavorable variances.
Kemper: Im afraid the final report is going to look even worse.
Ilianovitch: Oh?
Kemper: The line item for industrial engineering on the report is for work we hired Ferguson Engineering to do for us. The original contract was for $210,000, but we asked them to do some additional work that was not in the contract. We have to reimburse Ferguson Engineering for the costs of that additional work. The $189,000 in actual costs that appears on the preliminary draft report reflects only their billings up through December 21. The last bill they had sent us was on November 28, and they completed the project just last week. Yesterday I got a call from Laura Sunder over at Ferguson and she said they would be sending us a final bill for the project before the end of the year. The total bill, including the reimbursements for the additional work, is going to be . . .
Ilianovitch: I am not sure I want to hear this.
Kemper: $225,000
Ilianovitch: Ouch!
Kemper: The additional work added $15,000 to the cost of the project.
Ilianovitch: I cant turn in a report with an overall unfavorable variance! Theyll kill me at corporate headquarters. Call up Laura at Ferguson and ask her not to send the bill until after the first of the year. We have to have that $21,000 favorable variance for industrial engineering on the report. Required:
What should Tom Kemper do? Explain.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started