Question
1 Approved Answer
What type of chart compares the current project schedule with the original baseline schedule so that deviations from the original plan can be easily noticed?
What type of chart compares the current project schedule with the original baseline schedule so that deviations from the original plan can be easily noticed?
Multiple Choice
Project task tree
Project calendar
Tracking Gantt chart
Bar chart
Milestone chart