Question

1 Approved Answer

What will be the PERT weighted average for Activity A? Optimistic Estimate = 8 days Most Likely Estimate = 10 days Pessimistic Estimate = 24

image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
What will be the PERT weighted average for Activity A? Optimistic Estimate = 8 days Most Likely Estimate = 10 days Pessimistic Estimate = 24 days 141 O 12 10 18 Your cost performance index is 0.9 and the actual cost is 100. Calculate the earned value. 90 109 111 91 How is slack or float calculated? = task duration Latest finish date - duration Latest start date - earliest start date Earliest start date + duration What is the crashing technique used for? Network Diagramming Duration Compression Cost Reduction Activity Sequencing What is the crashing technique used for? Network Diagramming Duration Compression Cost Reduction Activity Sequencing

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: John J. Wild, Ken W. Shaw

2010 Edition

9789813155497, 73379581, 9813155493, 978-0073379586