What's the best activity that the project manager can do to ensure that all work that needs to get done for the project is included?
What's the best activity that the project manager can do to ensure that all work that needs to get done for the project is included? Question 11Select one: a. Lengthen the project objective statement b. Create and follow an accurate WBS c. Conduct a kickoff meeting and ensure that all team members are in sync d. Clearly define roles and responsibilitiesThe tasks in a WBS must be developed as a sequential list of steps. Question 12Select one: True False