When calculating the critical path for a three time estimate project, you use the as the activity duration time. optimistic time expected time pessimistic time

When calculating the critical path for a three time estimate project, you use the as the activity duration time.
optimistic time
expected time
pessimistic time
most likely time
Need help? Review these concept resources.
Read About the Concept
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: John A. Pearce II , Richard B. Robinson

12th Edition

007128950X, 978-0071289504

More Books

Students also viewed these General Management questions