When crashing a project, we should choose the node __________. Group of answer choices on the critical path with the lowest crash cost per period.
When crashing a project, we should choose the node __________. Group of answer choices on the critical path with the lowest crash cost per period. in the project with the average crash cost per period. in the project with the lowest crash cost per period. in the project with the highest crash cost per period. on the critical path with the highest crash cost per period