When developing a Gantt Chart,the process of giving a task some time to get started before the previous task is actually finished is called: (

When developing a Gantt Chart,the process of giving a task some time to get started before the previous task is actually finished is called: (LO5.2)
Lag Time
Finish-to-Start Time
Finish-to-Finish Time
Lead Time

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions