When evaluating a subcontractor's schedule, it is important to pay attention to the lag time values. Negative and/or large lag values indicate a resource constraint.
When evaluating a subcontractor's schedule, it is important to pay attention to the lag time values. Negative and/or large lag values indicate a resource constraint. Finish-to-start relationships with lag values of more than _________ days should be closely evaluated. 21 15 7 10