Question
1 Approved Answer
When evaluating independent projects with the NPV method, the decision rule is to accept all projects that have a positive NPV (NPV>0). Group of answer
When evaluating independent projects with the NPV method, the decision rule is to accept all projects that have a positive NPV (NPV>0).
Group of answer choices
True
False
Assume a project has a WACC equal to 10%. Other things held constant, an increase in the project's WACC will result in an increase in its NPV.
Group of answer choices
True
False