Question
1 Approved Answer
When is passive risk acceptance an appropriate approach? Question 9 options: A. When the likeliness of risk occurrence is very low. B. When the risk
When is passive risk acceptance an appropriate approach? Question 9 options: A. When the likeliness of risk occurrence is very low. B. When the risk occurrence is hard to identify. C. When it is best to deal with a risk as it occurs. D. When the risk cannot be assessed or analyzed