Question

1 Approved Answer

When Job 117 was completed, direct materials totaled $4,400; direct labor, $5,600; and factory overhead, $2,400. A total of 1,000 units were produced at a

When Job 117 was completed, direct materials totaled $4,400; direct labor, $5,600; and factory overhead, $2,400. A total of 1,000 units were produced at a per-unit cost of

a.$1,240

b.$124

c.$12.40

d.$12,400