When project teams use a change control system where all changes are evaluated for the potential value they bring to the project and the potential
When project teams use a change control system where all changes are evaluated for the potential value they bring to the project and the potential resources required, what does this prevent? Question 16 options: A. Scope creep B. Epics C. Work breakdown structure D. Scope decomposition