Question
1 Approved Answer
When reviewing the net present value graph for a project the higher the discount rate, the higher the NPV. the higher the discount rate, the
When reviewing the net present value graph for a project
the higher the discount rate, the higher the NPV. | ||
the higher the discount rate, the higher the IRR. | ||
the IRR will be a point on the horizontal axis line where NPV = 0. | ||
the IRR will always be a point on the horizontal axis equal to the required return |