Question

1 Approved Answer

When tasks, such as the highlighted tasks below, are indented in MS - Project or similar software this means: The tasks are off the critical

When tasks, such as the highlighted tasks below, are indented in MS-Project or similar software this means:
The tasks are off the critical path
The tasks are subtasks of a summary-level task
The tasks are predecessors of the prior task in the outline
The tasks are less important

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Process

Authors: Lee Long

4th Edition

978-0201822939,0201822938

More Books

Students also viewed these General Management questions

Question

Prove that if A attracts B, then A repels B .

Answered: 1 week ago