When the plan is ________ , a foundation exists for making public statements about expected project delivery dates. Question 2 options: complete, and the baseline
When the plan is ________ , a foundation exists for making public statements about expected project delivery dates. Question 2 options: complete, and the baseline established complete and the schedule established complete and the targets established complete and the resources established