When the planned level of activity is 900 units and the actual level of activity is 1,000 units, the total variable cost for supplies on
When the planned level of activity is 900 units and the actual level of activity is 1,000 units, the total variable cost for supplies on the flexible budget: should remain unchanged could be higher or lower than the actual cost of supplies should be higher than on the planning budget should be lower than on the planning budget Correct Answer could be higher or lower than the actual cost of supplies should be higher than on the planning budget