Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

When used properly, project management tools help project managers perform tasks with greater speed, accuracy, and efficiency. In this project 4, you and your fellow

When used properly, project management tools help project managers perform tasks with greater speed, accuracy, and efficiency. In this project 4, you and your fellow interns at PPI face the task of organizing all of the project documentation you produced manually and loading it into a project management software tool. Although not required, it may be advantageous for you and your fellow interns to agree on a software tool to use for this assumed project. A listing of free and open-source packages can be found in the course content section located on the left-hand navigation area of the blackboard. You are to work on the following tasks:

  1. Load your WBS from project three into the project management software package you selected.
  2. Provide a summary of your experience working with the project management software package and your observations regarding whether the software has calculated your schedule differently appropriately

Also, complete the following tasks with a description of each item:

  1. Run what-if simulations about schedules, costs, resources, and scope to understand how the project could change if some of its assumptions change. The process of running what-if can be found in your textbook
  2. Identify three scenarios for each element of the project?schedule, cost, resource, and scope?and run each simulation. Each simulation should include five changes to any aspect of the project. For example, in the what-if simulation about the schedule, you could see what happens if five activities increase in duration by X days. Provide a typical example with the calculations

Then, Submit the following items:

  1. A brief summary of the project plan components (package you selected) or identified (should be the Microsoft Project software) or Microsoft Excel for running what-if simulations.
  2. A page report that addresses the changes in the variables and the results of the simulation as well as any changes that occurred in your Gantt chart when generated by the selected project management software package as identified above. Include the following screenshots in the report:
    1. Project information
    2. Schedule simulation
    3. Cost simulation
    4. Resource simulation
    5. Scope creep simulation (Read about these from your textbook to understand)
image text in transcribedimage text in transcribed
ID Task Task Name Duration Start Finish Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 202 i Mode Jul Aug Sep Oct Nov Dec Jan 1 1 Mobile Application 82 days? Thu 8/18/22 Fri 12/9/22 N 1.1 Initiating 7 days Thu 8/18/22 Fri 8/26/22 3 1.1.1 Stakehokder 3 days Thu 8/18/22 Mor Identification 8/22/22 4 1.1.2 Project Charter 2 days Fri 8/19/22 Mon 8/22/22 UT 1.1.3 Kick-off meeting 2 days Tue 8/23/22 Wed 8/24/22 6 1.2 Planning 20 days Thu 8/25/22 Wed 9/21/27 1.2.1 Team planning 1 day Thu 8/25/22 Thu 8/25/22 h 8 1.2.2 Team charter 1 day Thu 8/25/22 Thu 8/25/22 9 1.2.3 Scope statement 3 days Fri 8/26/22 Tue 8/30/22 10 1.2.4 WBS 3 days Fri 8/26/22 Tue 8/30/22 11 1.2.5 Schedule and cost 16 days Wed Wed baseline 8/31/22 9/21/22 12 1.2.5.1 Task resources 4 days Wed 8/31/22 Mon 9/5/22 13 1.2.5.2 Task durations 3 days Tue 9/6/22 Thu 9/8/22 14 1.2.5.3 Task dependencies 3 days Fri 9/9/22 Tue 9/13/22 15 1.2.5.4 Draft Gantt chart 3 days Wed Fri 9/16/22 9/14/22 16 1.2.5.5 Final Gantt chart 1 day Mon Mon 9/19/22 9/19/22 17 1.2.6 Risk priorizitation 2 days Tue 9/20/22 Wed 9/21/22 - 18 1.3 Executing 45 days Thu 9/22/22 Wed 11/23/2 19 1.3.1 Survey 1 day Thu 9/22/22 Thu 9/22/22 20 1.3.2 User inputs 1 day Thu 9/22/22 Thu 9/22/22 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-or Deadline Project: Project1 Date: Fri 9/30/22 Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only L Inactive Milestone Finish-only Page 1ID Task Task Name Duration Start Finish Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 202 |Mode Jul Aug Sep Oct Nov Dec Jan 21 1.3.3 Application content 30 days Fri 9/23/22 Thu 11/3/22 27 1.3.4 Application design 20 days Thu 9/22/22 Wed 10/19/2 28 1.3.5 Application constructic 15 days Thu 10/20/22 Wed 11/9/22 29 1.3.6 Application testing 3 days Thu 11/10/22 Mon 11/14/2 30 1.3.7 Application promotion 2 days Tue 11/15/22Wed 11/16/2 31 1.3.8 Application roll-out 3 days Thu 11/17/22 Mon 11/21/2 32 1.3.9 Project benefits 2 days Tue Wed measurement 11/22/22 11/23/22 33 1.4 Monitoring and Controlling 3 days? Thu 11/24/2: Mon 11/28/2 34 1.4.1 Progress reports 3 days? Thu 11/24/22 Mon 11/28/2 35 1.4.2 Change request 3 days Thu 11/24/22 Mon 11/28/2 36 1.5 Closing 9 days Tue 11/29/2: Fri 12/9/22 37 1.5.1 Final project report 4 days Tue 11/29/22 Fri 12/2/22 38 1.5.2 Final project presentat 1 day Mon 12/5/22 Mon 12/5/22 39 1.5.3 Lessons learned 1 day Tue 12/6/22 Tue 12/6/22 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-or Deadline Project: Project1 Date: Fri 9/30/22 Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only L Inactive Milestone Finish-only Page 2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Hospitality Management

Authors: John R Walker

3rd Edition

0135061385, 9780135061381

More Books

Students also viewed these General Management questions

Question

Briefly describe how even parity and odd parity work.

Answered: 1 week ago

Question

7. How can the models we use have a detrimental effect on others?

Answered: 1 week ago