Question
When using the below information, calculate the rated capacity if increasing10%of the productivity. -No.of machines :10. -No of shifts :2. -Workers per shift :1shift-8workers.2shift-5workers. -Utilization=80%.
When using the below information, calculate the rated capacity if increasing 10% of the productivity.
- No. of machines : 10.
- No of shifts : 2.
- Workers per shift : 1 shift - 8 workers. 2 shift - 5 workers.
- Utilization = 80%.
- Efficiency = 90%.
- Working hours per week = 40 hours.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Heres the calculation of the rated capacity with a 10 productivity ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Management Accounting Information for Decision-Making and Strategy Execution
Authors: Anthony A. Atkinson, Robert S. Kaplan, Ella Mae Matsumura, S. Mark Young
6th Edition
137024975, 978-0137024971
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App