When using the 'yellow sticky' process to compute the expected time of the project network, all of these items should be followed or recognized as
When using the 'yellow sticky' process to compute the expected time of the project network, all of these items should be followed or recognized as true except: Question 14Select one: a. Work decomposes and flows from the top down b. Arrows indicate precedence c. Looping is not allowed d. Conditional statements are not allowed e. Create one yellow sticky for each task