When using _____________ to reduce a project schedule, certain activities are performed at a faster-than-normal pace. This often requires overtime pay but could also require
When using _____________ to reduce a project schedule, certain activities are performed at a faster-than-normal pace. This often requires overtime pay but could also require extra charges for expedited deliveries, more expensive machinery, or employing more skilled people. a. resource leveling b. crashing c. fast-tracking d. learning curve