Where can the project manager find work package information such as the code of an account identifier, a statement of work, information on the responsible
Where can the project manager find work package information such as the code of an account identifier, a statement of work, information on the responsible organization, quality requirements, and information on the required resources? Choose the best answer. WBS dictionary WBS Execution plan Project management plan