Which activities are part of the critical path? * (10 Points) Activity Immediate Predecessor A B Optimistic Most Likely Pessimistic 02 2 3 0.333
Which activities are part of the critical path? * (10 Points) Activity Immediate Predecessor A B Optimistic Most Likely Pessimistic 02 2 3 0.333 0.111 2 5 8 1.000 1.000 C 1 2 9 1.330 1.780 D A 5 5 5 0.000 0.000 E B, C 6 7 8 0.333 0.111 F B 14 14 14 0.000 0.000 G D, E 1 5 9 1.333 1.780 H G, F 8 1.167 1.362