Which is an example of bottom-up estimating? Portfolio manager assigns project completion dates for several projects Project manager assigns an experienced tester to estimate testing
Which is an example of bottom-up estimating? Portfolio manager assigns project completion dates for several projects Project manager assigns an experienced tester to estimate testing times Construction contractor allows each crew to estimate their task durations Project team adds a two-week buffer to the completion date for a risky project