Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Which is correct about the following: A)It is under budget and behind schedule. B)It is over budget and ahead of schedule C)It is under budget
Which is correct about the following:
A)It is under budget and behind schedule.
B)It is over budget and ahead of schedule
C)It is under budget and ahead of schedule.
D)It is over budget and behind schedule.
AC=1,345,000 PU=1,200.000 EV=1,135,000