Question: Which is NOT an option in the Update Project dialog box? Select an answer: You can assign overtime by bumping up assignment units. You can

Which is NOT an option in the Update Project dialog box?
Select an answer:
You can assign overtime by bumping up assignment units.
You can update only not started or completed tasks up to a chosen status date.
You can reschedule incomplete work to start after a certain date.
You can update every task (whether not started, complete, or in progress) up to a chosen status date.