Which is NOT found on an activity information checklist? Estimate of the time to complete the activity Risk having a significant impact Materials required to

Which is NOT found on an activity information checklist?

Estimate of the time to complete the activity

Risk having a significant impact

Materials required to complete the activity

Indication of critical path

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Rethinking Prestige Branding: Secrets Of The Ueber-Brands

Authors: Wolfgang Schaefer, J P Kuehlwein

1st Edition

0749470038, 9780749470036

More Books

Students also viewed these General Management questions

Question

Explain the use of a time log.

Answered: 1 week ago

Question

List several personal qualities that help people to be happy.

Answered: 1 week ago