Which is not true regarding the change orders? Select the most appropriate one. Owners frequently view the change orders as a result of the contractor's

Which is not true regarding the change orders? Select the most appropriate one.
Owners frequently view the change orders as a result of the contractor's lack of understanding of the contract.
Change orders can increase or decrease project costs.
The contractor should submit the official change order proposal to the owner.
Change orders should be initiated strictly by the project owner.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations management

Authors: Jay Heizer, Barry Render

10th edition

978-0136119418, 136119417, 978-0132163927

More Books

Students also viewed these General Management questions