Which of the answers below is NOT one of the three types of data that Microsoft Project uses to compute each assignment's cost value? a
Which of the answers below is NOT one of the three types of data that Microsoft Project uses to compute each assignment's cost value?
a Assignment work hours
b Task costs
c Resource standard rate
d Resource overtime rate