Which of the answers is NOT correct based on the MS Project screenshot below? A . Activities 1 . 3 . 2 and 1 .

Which of the answers is NOT correct based on the MS Project screenshot below?
A. Activities 1.3.2 and 1.3.3 have some works conducted in parallel.
B. Activity 1.6 is a milestone, which shows that the first stage can be completed on June 20.
C. Activities 1 and 1.3 are automatically scheduled.
D. Activities 1.3.2,1.3.3, and 1.3.4 are non-critical. We cannot crash them by adding new resources.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions

Question

11. The joint density of X and Y is f (x,y) = (y2 x2) 8 ey , 0

Answered: 1 week ago