Which of the conclusions cannot be drawn from the following Gantt chart (assuming the time unit is an hour)? ABCD E F + +
Which of the conclusions cannot be drawn from the following Gantt chart (assuming the time unit is an hour)? ABCD E F + + + + + + + 0 1 2 3 4 5 6 7 8 6 Activity E is not a critical activity. Activity D is not the predecessor nor the successor of activity F. It takes 7 hours to complete this project. The slack time of activity D is 1 hour.