Which of the following activities would you crash first? Activity Predecessor Normal Minimum Normal Crash Cost Time Time Cost ($) ($) A 3 3 1000
Which of the following activities would you crash first? Activity Predecessor Normal Minimum Normal Crash Cost Time Time Cost ($) ($) A 3 3 1000 1000 B A 10 8 1500 6000 C B 5 3 4000 6000 D C 7 6 7000 10000 E D 9 6 6000 12000 F E 15 10 1000 7000 Answer: [1]