Question

1 Approved Answer

Which of the following are NOT useful for developing an accurate estimate? Question 18 options: A) Historical data from similar past projects. B) Clear scope

Which of the following are NOT useful for developing an accurate estimate?

Question 18 options:

A)

Historical data from similar past projects.

B)

Clear scope described by approved specifications.

C)

Team members who will perform the work participate in estimating.

D)

Including the company's standard profit margin.

Question 19 (1 point)

ListenReadSpeaker webReader: Listen

A ballpark estimate is a good method for

Question 19 options:

A)

Quickly providing an estimate to screen out unrealistic options.

B)

All answers are correct.

C)

Manage expectations of key stakeholders to ensure realistic expectations.

D)

Using historical data to increase the accuracy of an estimate.

Question 20 (1 point)

ListenReadSpeaker webReader: Listen

After the team analyzes and prioritizes the threats, what is the most common response strategy to low probability, low impact threats?

Question 20 options:

A)

Mitigate the risk

B)

Monitor with a contingency plan

C)

Avoid the risk

D)

Accept the risk

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Hospitality Management Concepts And Cases

Authors: Alan Clarke, Wei Chen

1st Edition

0750666757, 9780750666756

More Books

Students also viewed these General Management questions

Question

What includes operational budgets?

Answered: 1 week ago