Which of the following descriptions about a critical path in a network diagram is FALSE? Group of answer choices Critical path activities may have non-zero
Which of the following descriptions about a critical path in a network diagram is FALSE? Group of answer choices Critical path activities may have non-zero slack. Crashing non-critical path activities has no impact on the project completion time. There may be multiple critical paths. The critical path determines the project completion time. Delaying an activity on a critical path delays the minimum time needed to complete the project