Which of the following elements are NOT required for a party to claim excuse for non-performance based on frustration? Group of answer choices The parties
Which of the following elements areNOTrequired for a party to claim excuse for non-performance based on frustration?
Group of answer choices
The parties to the contract assumed that the event that the party is relying on as a basis for the excuse would not likely occur
The existence of an event made performance by that party pointless
The party agreed to perform despite the event
The party did not wrongfully cause the event
Step by Step Solution
There are 3 Steps involved in it
Step: 1