Question
Which of the following events are considered significant in the evolution of operations management: a) cost focus b) quality focus c) customization focus d) globalization
Which of the following events are considered significant in
the evolution of operations management:
a) cost focus
b) quality focus
c) customization focus
d) globalization focus
e) all of the above
Question 7
ell designed WBS helps the project manager in that:
a) It defines all the elements of the project in a hierarchical
outline (map)
b) It defines the relationship of the projectto its subdeliverables,
and in turn, their relationships to work
packages
c) It serves as a framework for tracking cost and work
performance
d) All the above
Question 8
There are the following advantages to AON method:
a) No dummy activities are used
b) Nodes designate activities
c) Events are not used
d) Easy to draw if dependencies are not intense
e) All of the above
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started