Which of the following inputs is absolutely necessary to close a project or phase? A. Enterprise environmental factors B. Organizational process assets C. Accepted deliverables
Which of the following inputs is absolutely necessary to close a project or phase? A. Enterprise environmental factors B. Organizational process assets C. Accepted deliverables D. Closed procurements E. None of the above