Which of the following is Incorrect regarding a job - order costing system? Multiple Cholce Source documents are used to assign costs to the subsidiary
Which of the following is Incorrect regarding a joborder costing system?
Multiple Cholce
Source documents are used to assign costs to the subsidiary accounts.
Costs are accumulated for homogenous products that are produced through a continuous process.
Costs may be accumulated for a batch of work that contains many units of a product.
Unit cost is determined for each product or Job.