Which of the following is not an option for expediting when a project is underway. a. Focus on the critical path b. May order long-lead
Which of the following is not an option for expediting when a project is underway. a. Focus on the critical path b. May order long-lead time items early c. Get additional resources for overtime or more people d. Pull the resources from less critical activities e. May reduce scope