Question

1 Approved Answer

Which of the following is NOT the way for project managers to stay on schedule ( Refer to the assigned article Four ways project managers

Which of the following is NOT the way for project managers to stay on schedule (Refer to the assigned article "Four ways project managers can stay on schedule" in Ch5 website)
Question 4 options:
Add slack time into the project time schedule
Maintain the critical path of the project
Avoid crashing (e.g. reducing the completion time for tasks in the critical path) by any means.
Utilize the fast track tasks when necessary

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions

Question

American colonies independent from the British rule ?

Answered: 1 week ago

Question

Who was the principles author of the declaration of independence?

Answered: 1 week ago

Question

Main issue that caused the American civil war?

Answered: 1 week ago

Question

Which event marked the official end of the American civil war ?

Answered: 1 week ago