Question

1 Approved Answer

Which of the following is not true about liquidated damages? a They are harder to calculate up-front than the actual damages b They need to

Which of the following is not true about liquidated damages?

a They are harder to calculate up-front than the actual damages

b They need to be close to what the actual anticipated damages would be

c They are usually a flat amount that the parties agree to at the time of the contract

d They are good because it may hard to calculate the actual damages up-front

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Law Express EU Law

Authors: Ewan Kirk

7th Edition

1292295651, 978-1292295657

More Books

Students also viewed these Law questions

Question

Describe four technical features of Darwins theory of evolution.

Answered: 1 week ago