Which of the following is not true for the critical path? A It has zero float. B It's the shortest activity sequence in the network.

Which of the following is not true for the critical path?
A It has zero float.
B It's the shortest activity sequence in the network.
C You can determine which tasks can start late without impacting the project end date.
D It controls the project finish date.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Databases questions

Question

Name the four basic types of construction contracts.

Answered: 1 week ago

Question

=+a. What kind of personality does the brand have?

Answered: 1 week ago