Which of the following is not true for the critical path? A It has zero float. B It's the shortest activity sequence in the network.
Which of the following is not true for the critical path?
A It has zero float.
B It's the shortest activity sequence in the network.
C You can determine which tasks can start late without impacting the project end date.
D It controls the project finish date.