Which of the following provides a crosscheck on the validity of the budgeted cost for work performed (BCWP) claimed by a contractor? A. Technical performance
Which of the following provides a crosscheck on the validity of the budgeted cost for work performed (BCWP) claimed by a contractor? A. Technical performance measures (TPMs) B. Performance measurement baseline (PMB) C. Contract Funds Status Report (CFSR) D. Actual cost of work performed (ACWP)