Which of the following represents a constructive change to an existing contract? Instead of using the contractor's maintenance contract, the Government facilities manager takes a
Which of the following represents a constructive change to an existing contract?
Instead of using the contractor's maintenance contract, the Government facilities manager takes a laptop to a local repair shop because he does not have time to complete the appropriate maintenance request forms.
The Program Manager authorizes the contractor to begin work on a new task before the CO officially executes the task order
The contractor delivers supplies that meet contract requirements. However the COR sees opportunities for improvements that will better meet the Government's needs , and therefore sends the items back for corrections.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started