Question
1 Approved Answer
Which of the following scheduling errors prevents the calculation of the forward pass? A . Use of hard logic instead of soft logic B .
Which of the following scheduling errors prevents the calculation of the forward pass?
A Use of hard logic instead of soft logic
B Unwanted use of a constraint date
C Negative float
D A logic loop