Which of the following scheduling techniques takes into consideration the relationships among activities to determine the total completion time to complete a job? Group of
Which of the following scheduling techniques takes into consideration the relationships among activities to determine the total completion time to complete a job?
Group of answer choices
Gantt chart
Total Quality Management
Six Sigma
Critical path method