Which of the following statements about the critical path and critical chain methods of project scheduling is FALSE? Question 15 options: The critical chain can
Which of the following statements about the critical path and critical chain methods of project scheduling is FALSE? Question 15 options: The critical chain can be shorter than the critical path The critical chain includes resource constraints The critical path assumes unlimited resources The critical chain can be longer than the critical path None - all of the above statements are true
Step by Step Solution
There are 3 Steps involved in it
Step: 1