Which of the following statements does NOT describe how a Work Breakdown Structure ( WBS ) helps the Project Manager? Which of the following statements

Which of the following statements does NOT describe how a Work Breakdown Structure (WBS) helps the Project Manager?
Which of the following statements does NOT describe how a Work Breakdown Structure (WBS) helps the Project Manager?
Provides management with information appropriate to each organizational level.
Facilitates evaluation of cost, time, and technical performance of the organization on a project.
Helps manage plan, schedule, and budget.
Defines communication channels and assists in coordinating the various project elements.
None of the above

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Restaurant From Concept to Operation

Authors: John R Walker

6th Edition

9781118139950, 470626437, 111813995X, 978-0470626436

More Books

Students also viewed these General Management questions